1. Home
  2. |Insights
  3. |Start the Clock: Government’s Indirect Cost Rate Claim Accrued upon Submission of Indirect Cost Rate Proposal

Start the Clock: Government’s Indirect Cost Rate Claim Accrued upon Submission of Indirect Cost Rate Proposal

Client Alert | 2 min read | 02.22.24

In Strategic Technology Institute, Inc. v. Sec’y of Def., 91 F.4th 1140 (Fed. Cir. 2024), the Federal Circuit affirmed a decision by the Armed Services Board of Contract Appeals (ASBCA), which held that the government’s 2018 claim was not time-barred by the Contract Dispute Act’s (CDA) six-year statute of limitations.  The ASBCA found that the government’s claim did not begin to accrue until 2014, the date the government received the contractor’s indirect cost rate proposals for fiscal year (FY) 2008 and FY 2009. 

The Allowable Cost and Payment clause, FAR 52.216-7, governs the process for setting contractors’ annual final indirect cost rates that apply to certain types of cost-reimbursable and flexibly-priced contracts.  The clause requires contractors to submit annual final indirect cost rate proposals (sometimes referred to as incurred cost submissions) within six months after the end of the contractor’s fiscal year. 

Strategic Technology Institute (STI) did not submit its indirect cost rate proposals for FYs 2008 and 2009 until 2014, after the government notified the contractor that it had not received the submissions.  Following an audit of the proposed costs, in 2018 the contracting officer issued a final decision disallowing certain 2008-2009 direct and indirect costs and unilaterally setting STI’s final indirect cost rates for those years.  STI alleged that the government’s claim accrued when it billed those unallowable costs during 2008 and 2009 and then failed to timely submit its indirect cost rate proposals.  Therefore, the contractor asserted, the CDA’s six-year statute of limitations barred the government’s 2018 claim. 

The Federal Circuit disagreed, reiterating that, pursuant to FAR 33.201, a party’s claim accrues when “all events that fix the [other party’s] alleged liability and permit assertion of the claim were known or should have been known.”  Here, the government’s claim, which sought reimbursement of unallowable costs, penalties, and interest, accrued when STI submitted its indirect cost rate proposals in 2014.  Prior to that submission, the government had no basis to assert that STI’s billed costs were unallowable or to set the final indirect rates based on actual cost experience, and the contractor’s alleged liability for receiving overpayment was not fixed until it submitted unallowable costs in its indirect cost rate proposal.    

This decision is a reminder that the determination of when a party’s claim accrues, and thus whether it is timely, is highly fact specific and dependent on the basis of the claim.  When it comes to finalizing indirect cost rates, the government’s claim may not accrue until the contractor submits a final indirect cost rate proposal for that year containing sufficient information to put the government on notice of a potential claim.  Different facts may, of course, lead to a different result, as demonstrated by, for example, the ASBCA’s 2016 decision in Sparton DeLeon Springs, ASBCA No. 60416, 17-1 BCA ¶ 36,601 (finding that government’s claim for allegedly unsupported direct costs accrued when interim vouchers were submitted, not when the government conducted its audit of the contractor’s indirect cost rate proposal).

Insights

Client Alert | 2 min read | 11.20.24

CBCA Denies the Government’s Motion for Summary Judgment Based on an Issue of Fact Regarding the Contractor’s Reservation of Rights via a Transmission Email

In Fortis Industries, Inc., CBCA 7967 (Sept. 18, 2024), the Civilian Board of Contract Appeals (CBCA) denied in part the government’s motion for partial summary judgment on the issue of whether the contractor released its claims by signing a modification terminating the contract for convenience. During contract performance, the General Services Administration (GSA) imposed monthly deductions to contract payments as a response to certain performance issues. GSA later proposed to terminate the contract for convenience and sent a contract modification stating that all obligations under the contract were concluded except payment for work performed in June 2022. The contractor signed the modification but stated in its transmittal email that it was owed payment for services in May 2022 as well. ...