1. Home
  2. |Insights
  3. |Final Rule Requires Technical Interchange for IR&D Cost Allowability

Final Rule Requires Technical Interchange for IR&D Cost Allowability

Client Alert | 1 min read | 11.14.16

On November 4, 2016, DoD issued a final rule requiring contractors performing IR&D projects initiated in FY2017 or later to engage in a technical interchange with DoD, and report the occurrence of this interchange, before the costs for such projects may be deemed allowable (a topic previously discussed here). Although the rule is stated to be intended to promote DoD awareness of IR&D projects and provide feedback to contractors, it is likely to impose an administrative burden on contractors and DoD alike and could have a chilling effect on IR&D investment, particularly because it is silent regarding the allowability of IR&D costs if DoD fails to engage.

Insights

Client Alert | 1 min read | 08.10.26

ASBCA Denies Government Motion to Dismiss, Providing Key Guidance on Contractor Claim Standards Post-ECC International

In Appeal of Bahadir (a C&M case), the Armed Services Board of Contract Appeals denied the government’s motion to dismiss in its entirety, ruling in favor of the contractor on both key issues raised by the government. The case arises from a contract for construction work at Al Udeid Air Base in Qatar, under which Appellant alleged government-caused delay and filed certified prolongation claims using a “windows analysis” methodology. The government moved to dismiss, arguing that Appellant failed to state a sum certain for each of what the government characterized as 38 distinct claims, and separately that four claims had not been properly presented to the Contracting Officer. ...